PPM User Time Report Shows Incorrect Actual Time (Doc ID 1964913.1)

Last updated on AUGUST 21, 2016

Applies to:

Oracle Agile Product Portfolio Management - Version 9.3.1.2 to 9.3.3.0 [Release 9.3]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
PPM “User Time Report” for User reports Actual Time (In Days) as 38

EXPECTED
-----------
PPM “User Time Report” for this User should show Actual Time (In Days) as 0

FACTS
---------
Team tab of the Program shows the User did not report any Actual Hours, shows 0

Steps
--------
1. Run the PPM User Time Report


Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms