My Oracle Support Banner

20162917: Processing Lead Times Is Too Long Than Defined (Doc ID 1966481.1)

Last updated on FEBRUARY 03, 2019

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Goal

Ct experience the affect result of processing lead time is too long than expected when profile option 'MSO: Use Shift Definitions When Scheduling Lead Times' is set to 'Yes'.

For example, if manufacturing calendar is 8 hours -- 1 shift and post processing is 2 days, it will consider 48 hours / 8 hours = 6 days from dock date to due date.


 

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution
References


This document is being delivered to you via Oracle Support's Rapid Visibility (RaV) process and therefore has not been subject to an independent technical review.
My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.