20162917: Processing Lead Times Is Too Long Than Defined

(Doc ID 1966481.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Goal

Ct experience the affect result of processing lead time is too long than expected when profile option 'MSO: Use Shift Definitions When Scheduling Lead Times' is set to 'Yes'.

For example, if manufacturing calendar is 8 hours -- 1 shift and post processing is 2 days, it will consider 48 hours / 8 hours = 6 days from dock date to due date.


 

Solution