Original Duration Changed for Activities with Expected Finish.

(Doc ID 1967263.1)

Last updated on SEPTEMBER 03, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 6.0 and later
Primavera P6 Professional Project Management - Version 6.0 and later
Information in this document applies to any platform.


On : version, P6 Application

Original Duration changed when scheduling an in-progress activity with an Expected Finish.

Original Duration should not change when scheduling an in-progress activity.

The issue can be reproduced at will with the following steps:


Data Date of 15-Jan-15 and Activity A1000
1. User assigns Expected Finish 20-Jan-15
2. User Schedules with DD 15-Jan-15
3. Original Duration changes to 56.00h to honor Exp Finish, pulling Planned Start to 15-Jan-15
4. User marks A1000 as Started on 15-Dec-14
5. Schedule again and Original Duration stays at 56.00h

The issue has the following business impact:
Due to this issue, users cannot rely on the data for the Original Duration.

"Activity actual plus remaining duration does not equal at completion"


Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms