After R12 Upgrade From 11i, "Recommendations" Action In Supply Chain Planner Workbench Does Not Display "Flow Schedules"

(Doc ID 1983599.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, User Interface

ACTUAL BEHAVIOR
---------------
Migrating ASCP from Single Server (R11i Applications in Production) configuration to multi-server configuration. ASCP (R12.1.3), now resides in a separate Planning Server. Validation of planning in the new Planning Server looks good. However, in the Supply Chain Planner Workbench, when selecting the "Recommendations" Action, "Flow Schedules" for Flow item recommendations does not appear as a selection.

 

EXPECTED BEHAVIOR
---------------------
Looking into Flow items, there are Planned Orders for them so it seems that "Flow Schedules" should show recommendations just as it was in the old 11i ASCP.


STEPS TO REPRODUCE
---------------------
1) Open Supply Chain Planner Workbench
2) Drill down into the plan to the Recommendations exception level.
3) Flow Schedule is not seen in the list

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms