Wrong Planning Group Shown In The ASCP Planners Workbench For Projects. Collected Data Looks Correct

(Doc ID 1983862.1)

Last updated on JANUARY 07, 2016

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On 12.1.3.9.1 Memory Based Planner

The Planning group for a number of projects is incorrectly populated in ASCP workbench after the ASCP plan  run.

Sequence of events:
Users created a new Planning group as "BCL-1103213" under the Master Scheduling/MRP module. Further they modified the Project Parameters for a specific Project "1103213" in the Project Parameters form and changed the Planning group from "NP_ITALY" to the new "BCL-1103213".  After Data collections in Complete Refresh mode, they were able to see the orders with new Project-Planning Group combination in the Collected data as expected.
For Ex: (BCL-1103213, 1103213).

However inside the ASCP Planner workbench (after the plan run), they still see the old Planning Group - Project combination such as (NP_ITALY, 1103213).

Expected result should be to have the same data in Planner workbench as it is in Collected Data for Plan_id= -1.



Cause

Sign In with your My Oracle Support account