DRP FAIR SHARE ALLOCATION METHOD=CURRENT DEMAND RATIO NOT WORKING WITH CROSS INSTANCE PLANNING. (Doc ID 1985010.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3.8 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3.8 version, MSC 12.1.3 with VCP 12.1.3.8 Patch 14247039, running DRP plan options we tested the Fair Share Allocation Method setting it to Current Demand Ratio. We are not seeing any results from applying this option. We set up a scenario where the first period has less supply than demand expecting fair share to use the demand ratio calculation to assign the supply to the organization with the highest demand for that planning period in accordance to the user quide documentation.
The results was the supply was assigned to the Organization with lower demand for the first planning period. This was the initial result as well prior to using the fair share option.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users Demand Ratio is not correctly assigning the supply to the organization with the highest demand for that planning period.

Cause

Sign In with your My Oracle Support account