ECC Classic Plan Is Not Offloading Planned Orders From Primary Routing To Alternate Routing (Doc ID 1985019.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.2.2 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.2 version, Memory Based Planner

ACTUAL BEHAVIOR
---------------
ECC Classic plan is not offloading planned orders from Primary Routing to Alternate Routing. In other words, ECC Classic plan is suggesting planned orders using Primary Routing and generating Late replenishment exception messages. Whereas, plan can suggest planned orders using Alternate Routings to avoid late replenishment of demands.

EXPECTED BEHAVIOR
-----------------------
Expect the plan to use the alternate routing

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Setup alternate routings
2. Run the ECC Plan
3. Note that the alternate routings do not get used

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms