Symptoms

On : 12.2.2 version, Memory Based Planner

ACTUAL BEHAVIOR
---------------
ECC Classic plan is not offloading planned orders from Primary Routing to Alternate Routing. In other words, ECC Classic plan is suggesting planned orders using Primary Routing and generating Late replenishment exception messages. Whereas, plan can suggest planned orders using Alternate Routings to avoid late replenishment of demands.

EXPECTED BEHAVIOR
-----------------------
Expect the plan to use the alternate routing

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Setup alternate routings
2. Run the ECC Plan
3. Note that the alternate routings do not get used

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


This document is being delivered to you via Oracle Support's Rapid Visibility (RaV) process and therefore has not been subject to an independent technical review.
My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.