ASCP seem to show incorrect pegging - splitting the pegged qty into fractions for the same supply
example

Part#10017676-001 has two Work Order demands:
1.From assembly 10017673-001 which has WO#17077403 for qty 4.This WO needs 4 of component 10017676-001 but 3 of these are already issued to the WO
so the WO demand for 10017676-001 now = 1.

2.From assembly 10017673-001 which has WO#17206564 for qty 4.This WO needs 4 of component 10017676-001 and all of the quantities are open
so the WO demand for 10017676-001 originating from this WO is 4.


Component 10017676-001 has a WO#17079385 for qty 2 and the pegging shows this information

1.Qty 1 of this WO pegged to WO demand of 4 originating from WO 17206564 (point 2 above).This is correct
2.Qty .25 of this WO is pegged 4 times to WO demand of 1 originating from WO 17077403 (point 1 above) instead of showing 1 line of qty 1
of this WO pegged to qty 1 of WO demand originating from WO 17077403 .This appears to be incorrect - we expect the qty 1 to be pegging to a single end demand.

There are no order modifiers on either 10017673-001 or 10017676-001
Shrinkage rate is not setup for either 10017673-001 or 10017676-001
Yield = 1
 

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution
References


This document is being delivered to you via Oracle Support's Rapid Visibility (RaV) process and therefore has not been subject to an independent technical review.
My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.