Symptoms

On : 8.3.1.0 version, P6 Application

ACTUAL BEHAVIOR
---------------
User cannot edit Remaining Units on Resource Assignments in P6 Web. User is able to edit Remaining Units in P6 Client.

EXPECTED BEHAVIOR
-----------------------
User should be able to edit Remaining Units on Resource Assignments in P6 Web.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Attempt to edit Remaining Units in P6 Web but field is not editable.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot properly update the projects.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms