Goal

 In Flow Manufacturing environment, during review of plan, I have observed that - Planned Order of component item has been created and pegged to a parent item planned order where Due date of planned order on component item is exactly same as due date of planned order on parent item. Logically Planned order due date of component item must be same as Start date of Planned order on parent item

Solution