MetaSolv Plan Task Checklists Not Getting Assigned to Tasks

(Doc ID 2002607.1)

Last updated on MAY 22, 2018

Applies to:

Oracle Communications MetaSolv Solution - Version 6.2.1 and later
Information in this document applies to any platform.

Symptoms

MSS Version 6.2.1 Work Management  and Tasks Check List

======================================

Checklists are not getting assigned to task when they are assigned.

Problem Description:

When there is a RULE setup in Rules and Behavior to delete a task from the provisioning plan during task generation, the check list items  disappear for the follower tasks in the Work Queue manager.