ASCP Is Scheduling Planned Orders For Phantom Items That Are No Longer Active (Doc ID 2005191.1)

Last updated on FEBRUARY 19, 2019

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, Constrained planning in Test

PROBLEM
-------------
ASCP is scheduling planned orders for items that are no longer active . Users have two components inside a BOM one (Phantom item A) of them has an end effectivity date of 27 apr 2015 and the other one (Phantom item B) has start date of 28 apr 2015 and no end date.  When they perform the data collection on ASCP instance everything looks fine, but when run the Classic Constrained plan, ASCP generates double supply, one for the Phantom item A and other for the Phantom item B.

Users expected see just one supply, not both.

STEPS
--------
1. Create an item with a phantom component that will have an end effectivity and a new phantom item effective the following day
2. Create a bom for the phantom component.
3. Run data collections and the ASCP  plan.
4. Release a planned order for the parent item in the ASCP planners workbench.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.