Exchanging (cost-loaded) schedules via XER files between different P6 databases results in decreased Activities Budgeted Total Costs dollar amounts. (Doc ID 2006207.1)

Last updated on FEBRUARY 13, 2017

Applies to:

Primavera P6 Professional Project Management - Version 8.3 and later
Information in this document applies to any platform.

Symptoms

After an XER Import and either Creating New OR Updating Existing Project, any cost-loaded activities are losing their total cost amount (sometimes down to $0.00).

Cause