Tasks Not Added In Proper Sequence Through Rules & Behaviours
(Doc ID 2008820.1)
Last updated on OCTOBER 01, 2024
Applies to:
Oracle Communications MetaSolv Solution - Version 6.0.15 and laterInformation in this document applies to any platform.
Symptoms
When a PSR is created with 2 specific rules - (PROVISIONING PLAN = BB - Modify Order (MO) OR PROVISIONING PLAN = CLEC BB Modify Order (MO)) AND (PRODUCT = PIN Change Required OR PRODUCT = NSP Change) and (PROVISIONING PLAN = BB - Add Order (OR) OR PROVISIONING PLAN = BB - Modify Order (MO)) AND (PRODUCT = No PINs Available OR PRODUCT = Max Subs Exceeded)
The task created to perform this action doesnt get added before PCONDES, and is shown without any dependency.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |