Total Supply Value Mismatch Between ASCP And APCC (Doc ID 2014184.1)

Last updated on JUNE 28, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.2.3 to 12.2.4 [Release 12.2]
Information in this document applies to any platform.
MSCFNSCW
MSCPHOPB.pls

Symptoms

Using Advanced Supply Chain Planning / User Interface / Horizontal Plan
On EBS 12.2.3 through 12.2.4.1
When attempting to confirm results reported by APCC to results reported by ASCP Horizontal Plan,
find that the ASCP Horizontal Plan does not include On Hand in the Total Supply measure in the ASCP plan.

EXPECTED BEHAVIOR
-----------------------------------
Expect that the ASCP Horizontal Plan does include On Hand in the Total Supply measure in the ASCP plan per the design change implemented in
<Bug 17351290> - TOTAL SUPPLY SHOULD INCLUDE ON-HAND WHEN BEING CALCULATED IN ASCP.

-- Steps To Reproduce:

Customer states the issue can be reproduced at will at customer site with the following steps:
1. (R) Advanced Supply Chain Planner
2. Open the (material) Horizontal Plan and inspect the Total Supply measure in the first bucket
3. Observe that Total Supply does not include Beginning On Hand for that bucket

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms