ASCP Does Not Consider PIP (Planned Inventory Point) (Doc ID 2015602.1)

Last updated on JUNE 28, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.2.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.3 version, Memory Based Planner

ACTUAL BEHAVIOR
---------------
ASCP does not consider PIP ( Planned inventory point)

Business wants to use Oracle PIP functionality. When we tried to model it, as per PIP functionality, ASCP is not considering the PIP point to not recommend supply orders (work orders) for cancellation when the end item demand is cancelled due to various reason.

It behaves as if PIP is not turned on and recommending final assembly orders and sub assembly orders to be cancelled which is not correct.


EXPECTED BEHAVIOR
-----------------------
PIP should work as designed.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms