Enhancement - Increase Size of Task Work Interval Business Days to 3 Digits
(Doc ID 2017153.1)
Last updated on MAY 04, 2021
Applies to:
Oracle Communications MetaSolv Solution - Version 6.2.1 and laterInformation in this document applies to any platform.
**** Enhancement released in Patch 26557511 for MSS 630.b639 on 1/16/2018. ****
Goal
REQUIREMENT
User wants increased the size of MSS Task's Work Interval Bus Day Limits (Duration days) to support 3 digits.
Window: w_prov_plan_maint
BUSINESS JUSTIFICATION
Users need to set the Work Interval Bus Day for a task to 103 days, however
the GUI will only allow to enter two digits which would be a max to 99.
The Work Interval Bus Days is stored in table ASAP.PROVISIONING_PLAN_TASK,
column COMPLETION_DAYS that is a variable type NUMBER(2,0) so, the maximum is 99.
There is no Preference to change this parameter.
Solution
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Goal |
Solution |
ENHANCEMENT REQUEST |
UPDATES: ER Released in Patch 26557511 for MSS 630.b639 |
References |