Enhancement - Increase Size of Task Work Interval Business Days to 3 Digits

(Doc ID 2017153.1)

Last updated on JANUARY 16, 2018

Applies to:

Oracle Communications MetaSolv Solution - Version 6.2.1 and later
Information in this document applies to any platform.
**** Enhancement released in Patch 26557511 for MSS 630.b639 on 1/16/2018. ****

Goal

REQUIREMENT

User wants increased the size of MSS Task's Work Interval Bus Day Limits (Duration days) to support 3 digits.
 
 Window: w_prov_plan_maint

 

BUSINESS JUSTIFICATION

 Users need to set the Work Interval Bus Day for a task to 103 days, however
 the GUI will only allow to enter two digits which would be a max to 99.

The Work Interval Bus Days is stored in table ASAP.PROVISIONING_PLAN_TASK,
column COMPLETION_DAYS that is a variable type NUMBER(2,0)  so, the maximum is 99.
There is no Preference to change this parameter.

 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms