Planned Order Demands Are Getting Pulled In Previous Planning Bucket (Doc ID 2018416.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3.7 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3.7 version, Memory Based Planner

ACTUAL BEHAVIOR
---------------
You have item A with a 2 forecasts due one 31-MAY-2015 with the following values:
- 706.7
- 293.3

When the plan runs, a Planned Order is generated with a Sugg Start Date and Sugg Due Date of 31-MAY-2015. This is all good.

The problem is that the component for this item is having a due date on 30-APR-2015 even though there is 0 lead time for this item.

EXPECTED BEHAVIOR
-----------------------
Expectation is that the component would not be due 1 month prior.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Run the plan


Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms