Show "No Privilges" In My Assignment When Task Owner Not In Project Team Tab (Doc ID 2018975.1)

Last updated on AUGUST 08, 2017

Applies to:

Oracle Agile Product Portfolio Management - Version 9.3.3.0 and later
Information in this document applies to any platform.

Symptoms

On : 9.3.3 version, Show "No Privilges" in My Assignment when task owner not in project team tab

EXPECTED BEHAVIOR
-----------------------
Expect to see the root level parent project under My Assignment tab

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1.Create a new Project, by userA
2,Add Task1 to the Project
3,Delegate Task1 to UserB
4,Login as UserB, goto My Assignment tab
5,In RelatedTo field, show "No Priv"

BUSINESS IMPACT
-----------------------
Users unable to see root level project from My Assignment tab

Cause