PS: Manually Created Work Order Is Not Scheduled as Per CRO User Defined Ideal Sequence

(Doc ID 2033774.1)

Last updated on JUNE 28, 2017

Applies to:

Oracle Production Scheduling - Version and later
Information in this document applies to any platform.


When a work order is manually added to a PS model and solved, PS doesn't sequence the new work order correctly as per CRO user defined ideal sequence setup. New manually created work order is scheduled at the end of the operation sequence rather than following the CRO user defined ideal sequence