Business Process Status Not Updating When Attempting Update Via Email (Doc ID 2041187.1)

Last updated on MARCH 01, 2017

Applies to:

Primavera Unifier Cloud Service - Version 10.0 and later
Primavera Unifier - Version 10.0 and later
Information in this document applies to any platform.

Symptoms

BP status is not changing when updating via email

FOR EXAMPLE:

ACTUAL BEHAVIOR
---------------
When clicking "Approve Budget Approval" from email (in this example a Gmail account), the status does not change to Approved.

EXPECTED BEHAVIOR
-----------------------
The status should be updated when approving from the email.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Login to Unifier
2. On the left top of the screen, find bookmarks
3. Click on “Budget Approval” to navigate to the project and Budget Approval BP
4. Create a record and send for Approval
5. Login to the email account with the given credentials to Approve the record

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot properly approve BPs via email which reduces their efficiency.

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms