Risk Results More Optimistic When Calculated From Mitigated Plans as Weather Risk Not Impacting Tasks or Lag (Doc ID 2041597.1)

Last updated on JULY 27, 2017

Applies to:

Primavera Risk Analysis - Version 8.0 to 8.7.0056 [Release 8.0 to 8.7]
Information in this document applies to any platform.

Symptoms

The Risk Results calculated in the deterministic plan produce worse results than Risk Results calculated in Mitigated plans. The Mitigated plans have additional Risks assigned from the Risk Register therefore one would expect the Mitigated plan's Risk Results to be worse.

Cause