RP - Planned Order Recommendations On Non-working Days, Due Date Calculation Not Correct (Doc ID 2042353.1)

Last updated on FEBRUARY 03, 2019

Applies to:

Oracle Rapid Planning - Version 12.2.3 and later
Information in this document applies to any platform.

Symptoms

12.2.3

PROBLEM
-------------
We see the below with 7/22 as plan run date:-
Need by date: 8/10/2015 (The earliest demand due date that the supply is pegged to)
Suggested Due Date for planned order: 8/1/2015 – In an unconstrained plan this should match the Need by Date and should be 8/10/2015. 8/1 also happens to be a non-working day

Attached are screenshots highlighting the issue. Also attached is the excel extract of Supply and Demand tab and the DAT files

STEPS
--------
Run the plan and check results.
MSC: Calendar Reference for Bucketing - NULL
Plan owning org is WH8
Org with problem is WH2
Both orgs have same calendar assigned and it has 01-AUG as off day

EXPECTED BEHAVIOR
----------------------------
Supply and demand are properly aligned

BUSINESS IMPACT
----------------------
cannot use this plan output

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


This document is being delivered to you via Oracle Support's Rapid Visibility (RaV) process and therefore has not been subject to an independent technical review.
My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.