RP - Planned Order Recommendations On Non-working Days, Due Date Calculation Not Correct
(Doc ID 2042353.1)
Last updated on FEBRUARY 27, 2019
Applies to:
Oracle Rapid Planning - Version 12.2.3 and laterInformation in this document applies to any platform.
Symptoms
12.2.3
PROBLEM
-------------
We see the below with 7/22 as plan run date:-
Need by date: 8/10/2015 (The earliest demand due date that the supply is pegged to)
Suggested Due Date for planned order: 8/1/2015 – In an unconstrained plan this should match the Need by Date and should be 8/10/2015. 8/1 also happens to be a non-working day
STEPS
--------
Run the plan and check results.
MSC: Calendar Reference for Bucketing - NULL
Plan owning org is WH8
Org with problem is WH2
Both orgs have same calendar assigned and it has 01-AUG as off day
EXPECTED BEHAVIOR
----------------------------
Supply and demand are properly aligned
BUSINESS IMPACT
----------------------
cannot use this plan output
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |