Resource Usage Profile Does Not Display Units For Closed Projects. (Doc ID 2044263.1)

Last updated on JUNE 27, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 15.1.3.0 to 15.1.4.1 [Release 15.1]
Information in this document applies to any platform.

Symptoms

Resource Usage Profile does not display units for closed projects.

In P6 Professional, under Resource Assignments, only units from open projects are shown, despite having under User Preferences, Resource Analysis the selection "All closed projects (except what-if projects)" is flagged.


ACTUAL BEHAVIOR  
---------------
Resource usage profile does not display units for closed projects.

EXPECTED BEHAVIOR
-----------------------
Resource usage profile does to display units for closed projects.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Edit, User Preferences, Resource Analysis, select 'All closed projects
(except what-if projects)'.
2. Create two projects, each project with one activity.
3. Assign one resource to those two activities with same budgeted units and
Remaining Units.
4. Run summarize on those two projects.
5. Close one project, view Resource Usage Profile, change display to Show All
Projects.
6. Found the resource remaining units are same when click to Show All
Projects or Open Projects Only, the closed project units are not shown in the
profile.


BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot view resource usage profile when project is closed.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms