Goal

MSC: Use Enhanced Forward ATP

==========================

We want to implement the profile MSC: Use Enhanced Forward ATP to No at site level . Currently it is set to Yes. I am doing some testing for this profile and I am seeing some difference in the ATP dates for the same item with Profile Set to No at site level and with profile set to Yes.

Below is the Detail Summary :

Item : A
Destination Org : B
Source Org : S.

Intransit Lead Time from S to B: 56 days.

Pre -Processing Lead time in Destination Org ( B) : 1 day

Processing Lead time in Destination Org (B) - 30 day

Post Processing Lead time in Destination Org (B) -2 day.

With Profile MSC: Use Enhanced Forward ATP set to NO at site level :

For a request date of 06-Aug-2015 ATP inquiry is giving the arrival date of 06-Oct-2015 which I believe is calculated adding the 56 days calendar days of Intransit Lead time plus 2 days of post processing lead time in Destination Org.

But When I set this profile to Yes at site level for the same item and for the same request date ATP inquiry form is giving me the arrival date of 05-Oct-2015.

We would like to understand why these difference in days are coming with change in profile setting.
Investigating results in ATP inquiry form for the item A.

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms