Predecessors Cannot be Added in the Schedule Sheet Grid

(Doc ID 2047081.1)

Last updated on JUNE 29, 2016

Applies to:

Primavera Unifier Cloud Service - Version 10.0 and later
Primavera Unifier - Version 10.0 and later
Information in this document applies to any platform.

Symptoms

When adding predecessors by directly editing the cell in the Schedule sheet, the changes are not kept.

Cause