Max Resource Units/Time Are Displayed Incorrectly In Resource Assignment View. (Doc ID 2047358.1)

Last updated on JULY 05, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.3.7.0 and later
Information in this document applies to any platform.

Symptoms

On : 8.3.7.0 EPPM version, P6 Web Application.

ACTUAL BEHAVIOR
---------------
"Max Resource Units/Time" in Resource Assignment View are not shown correctly. In most cases the value is 0.

EXPECTED BEHAVIOR
-----------------------
If Default Units/Time is configured, the value for "Max Resource Units/Time" in Resource Assignment View should not be 0.

STEPS TO REPRODUCE:
1. Log into P6 Web.
2. Go to Resources, Assignments.
3. Filter view for Problem Project.

Have Resource ID and Max Resource Units/Time amongst columns in View.

Compare the displayed Max Resource Units/Time values with the default Units/Time from Resources, Administration tab.

Several Resource effective dates with different Max Units per Time required (e.g. 10 % up to 200 %).

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms