LIOOB Event Code In Multiple Activity Resource Replace

(Doc ID 2049259.1)

Last updated on MARCH 16, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version and later
Primavera P6 Professional Project Management - Version and later
Information in this document applies to any platform.


When attempting to replace a resource against multiple activities, the following error occurs.

An application event has been intercepted. Please note the event code for reference
Event code LIOOB-3801-6.

The issue can be reproduced at will with the following steps:

1. Open sample project.
2. Select Assign Resource from Assign toolbar.
3. Select all activities.
4. Select one resource in Assign Resource dialog then click Replace.
5. Select any resource then Assign.

The issue has the following business impact:
Due to this issue, users cannot replace a resource on multiple activities successfully.


Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms