Using SQLite, When Exporting a P6 Project XML From The Client, the Nonworking Days Appear as Working

(Doc ID 2051053.1)

Last updated on SEPTEMBER 29, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 15.1.1.0 and later
Information in this document applies to any platform.

Symptoms

 Using SQLite, when exporting a P6 Project XML from the client, the nonworking days appear as working.

 

---------- STEPS TO REPRODUCE

1. Go to P6 client (SQLite database)and open the sample data Project EC00610 Harbour Pointe Assisted Living Centre.

* The calendar for this project is 'Trades 5 Day Workweek' and the day 2001-07-04 is a non-working day.

2. Select File, Export, Primavera P6 XML.

3. Open the XML in a browser and search for that date:

The date should show as:

 HolidayOrException> 

<Date>2011-07-04T00:00:00</Date> 

<WorkTime xsi:nil="true" /> 

</HolidayOrException>

 

 It shows as:

 <HolidayOrException>       

 <Date>2011-07-04T00:00:00</Date>      

 <WorkTime>         

 <Start>00:00:00</Start>        

 <Finish>23:59:00</Finish>     

 </WorkTime>     

</HolidayOrException>
 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms