Why isn't the Performance Percent Complete value in the WBS 100 as expected? (Doc ID 2055413.1)

Last updated on SEPTEMBER 16, 2015

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 7.0 SP1 and later
Information in this document applies to any platform.

Goal

On : PPM 7.0 SP1 version, P6 Application

Why does Performance Percent Complete not display 100% as expected?

Solution