Data Date Changes When Scheduling Using "All Projects Use Their Own Data Date" Option

(Doc ID 2056926.1)

Last updated on SEPTEMBER 30, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 15.1.3.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
When using the "All projects use their own Data Date" option when scheduling, the project Data Date is not upheld.

EXPECTED BEHAVIOR
-----------------------
Expect project Data Date to remain intact.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:



Cause