Can The "Copy Project" Service Be Run As A Scheduled Job Per The Documentation Noted Within The Cumulative Feature Overview Tool? (Doc ID 2057235.1)

Last updated on DECEMBER 19, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.4.0.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL RESULTS
-----------------
Within the Cumulative Feature Overview Tool, found on the Oracle Technology Network, it states:

In actuality, users cannot schedule a Copy Project, at a particular time frame, within P6. Instead, the Copy Project service can only be run as an ASAP (on-demand) job and not as a scheduled job per the Cumulative Feature Overview tool documentation.


EXPECTED RESULTS
-----------------
For the Copy Project service to run as a scheduled job instead of only an ASAP (on-demand) job.

Cause

Sign In with your My Oracle Support account