Symptoms

On :  12.2.3 version, Memory Based Planner

ACTUAL BEHAVIOR  
---------------
Purchase Order pushed out to item lead time in ECC plan when late to sales order  

I have a purchase order which is not firm with old due date a few days past due and it is being pushed out to end of December which is exactly the 84 day lead time of this item in workdays, yet the sales order is satisfied late.  
We are running an ECC plan and there are no other constrained causing this PO to be pushed out.

The source instance is JD Edwards.

EXPECTED BEHAVIOR
-----------------------
Expect the PO to not get pushed out

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Run the ECC Plan
2. Note that the PO is pushed out for no apparent reason

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms