Primavera Gateway 15.1 - EBS to P6 Synchronization - WBS and Activities Not Imported to P6

(Doc ID 2060073.1)

Last updated on JANUARY 06, 2016

Applies to:

Primavera Gateway - Version 15.1.0.0 and later
Information in this document applies to any platform.

Symptoms

When running a EBS to P6 synchronization and executing Import Project Data Business Flow by selecting the Project Plan Parameter as "Financial Plan" WBS can be imported to P6.
However executing the same business flow by selecting the Project Plan as "Work Plan" the WBS/Activities are not imported to P6. Only Project ID and Project Name are imported in P6.

Cause

Sign In with your My Oracle Support account