When Importing Expenses from Excel, Budgeted Cost is Getting Set to 0. (Doc ID 2064235.1)

Last updated on OCTOBER 09, 2015

Applies to:

Primavera P6 Professional Project Management - Version 15.1.0.0 and later
Information in this document applies to any platform.

Symptoms

When Importing Expenses from Excel, Budgeted Cost is Getting Set to 0.

When trying to import Expenses that don't exist into a Schedule, it imports Budgeted Cost as Price/Unit, but Price/Unit is something marked with an asterisk (*), therefore, it shouldn't let you modify it through Excel.

Cause

Sign In with your My Oracle Support account