The Plan Recommends Many Planned Orders On The Same Date In May 2016 - 8 Months From Sysdate

(Doc ID 2066713.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

Any release

PROBLEM
-------------
Item has all demand from 06-MAY-2016 to end of plan - 31-JAN-2017 (19 demands ) having planned orders on 06-MAY-2016
19 planned orders on 06-MAY-2016 for fixed lot multiplier of 1100000
- appears to be Make AT item

ECC plan - no decision rules
0 days / 52 weeks / 12 periods

STEPS
--------
Run plan - check results

EXPECTED BEHAVIOR
----------------------------
planned order meet demands on time - not early

BUSINESS IMPACT
----------------------
wrong plan output - cannot use the output

Cause

Sign In with your My Oracle Support account