Form F_RQS_10 Shows Percent Complete Total as 0 and Work Completed Stored to Date Total Does Not Show Decimal Amount (Doc ID 2067295.1)

Last updated on MARCH 02, 2017

Applies to:

Primavera Contract Management - Version 14.1 and later
Information in this document applies to any platform.

Symptoms

Requisition form F_RQS_10  is showing Percent Complete column total as 0, and the Work Completed and Stored Materials to Date column total does not show decimal amount.