When Using The Auto Submission Option PEND_HR_CNT does not match with HR_CNT (Doc ID 2067573.1)

Last updated on NOVEMBER 04, 2015

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 15.1.0.0 to 15.1.1.1 [Release 15.1]
Information in this document applies to any platform.

Symptoms

On : Prior 15.1.1.0 version, P6 Progress Reporter / Timesheets

ACTUAL BEHAVIOR  
---------------
When using the Time Approval option of Auto Submission making changes to a Timesheet are not pushed into the RSRCHOUR.HR_CNT field.  Initially when hours are added into an activity they stay in RSRCHOUR.PEND_HR_CNT until approved. However, when changing actuals put in on an activity the changes only reflect in PEND_HR_CNT and not in HR_CNT

EXPECTED BEHAVIOR
-----------------------
For PEND_HR_CNT to match HR_CNT when using Auto Submission

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Set Timesheet Approval options to "Auto Submission" (Administer > Application settings > Timesheet)
2. Create a Project with one activity
3. Create a Resource, make it use timesheets and assign it to a user
4. Assign the resource to an activity
5. Log into PR
6. Put actuals hours on at least one day on the activity
7. Query the database for the PEND_HR_CNT and HR_CNT
8. Notice they match
9. Change one actual to a different number
10. Query the database for the PEND_HR_CNT and HR_CNT
11. Notice they are different

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms