Primavera P6 Professional Performance Issue when Leveling Project (Doc ID 2068661.1)

Last updated on OCTOBER 22, 2015

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 6.2.1 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
Specific project is taking longer to run the leveler, whereas other projects with similar number of activities are taking 4 or 5 minutes to complete the leveling process.


EXPECTED BEHAVIOR
-----------------------
For the leveling process of specific projects to complete in the same amount of time other projects with a similar activity account complete in.

Cause