Project Start Date Equals Baseline Start When Project is Closed (Doc ID 2070085.1)

Last updated on OCTOBER 26, 2015

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.3.2.0 to 8.3.9.0 [Release 8.3]
Primavera P6 Enterprise Project Portfolio Management - Version 8.4.0.0 to 15.1.6.0 [Release 8.4 to 15.1]
Primavera P6 Enterprise Project Portfolio Management - Version 15.2.0.0 and later
Information in this document applies to any platform.

Symptoms

On : P6 Application

ACTUAL BEHAVIOR
---------------
Project Start date matches Baseline Start date in Projects view when Project is closed, even if Project has been summarized.

EXPECTED BEHAVIOR
-----------------------
Expect Project Start date to match Project Start date.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Log into the Professional Client.
2. Projects view.
3. Notice Project Start date incorrect and takes on Baseline Start if Project is closed. Project has been summarized.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot view the correct date in the Projects view.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms