PPM Dependencies Schedule Start and End Date Stopped Working After Some Time In Templates (Doc ID 2070782.1)

Last updated on AUGUST 08, 2017

Applies to:

Oracle Agile Product Portfolio Management - Version 9.3.4.0 and later
Information in this document applies to any platform.

Symptoms

Dependence task does not changed the start/end date.

The start/end date doesn't change after dependency setup
Web client shows wrong start/end date
Gantt Chart graphic date doesn't change

Steps to reproduce:
1. login web client
2. try any PPM template under Recently Visited
3. select 2 tasks and add the dependency - observe the start/end date change; the start/end date does not change
4. launch to Gantt Chart and do the same steps as #3 - the dependency is linked but the graphic doesn't move


Cause