The MRP plan does not consider the seventh decimal place (Doc ID 2074562.1)

Last updated on SEPTEMBER 30, 2024

Applies to:

Oracle Materials Requirement Planning - Version 12.0 and later
Information in this document applies to any platform.

Goal

When BOM define as follows, MRP plan do not create Planned order demand for ItemC.

Steps:

1. Create BOM
   ItemA (Assembly)
    + ItemB (sub assembly)     Qty:1
      + ItemC (component)       Qty:0.0000008 (seventh decimal place)

2. Create MDS for ItemA as Qty:1000

3. Launch MRP Plan

4. MRP WORKBENCH > Supply/Demand

Item Order Type Qty Action
ItemB Planned Order 1000 Release
ItemB Planned Order demand -1000 Demand
ItemA Manual MDS -1000 Demand
ItemA Planned Order 1000 Release

 

As the results, there is no Planned Order demand for ItemC.

This issue always occurs when Qty set as seventh decimal place.

If the case of sixth decimal place, Planned Order demand for ItemC is generated.

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!