How Does the Setting "Hide Empty Projects or WBS Threshold" Configured in P6 Administrator Work? (Doc ID 2075713.1)

Last updated on NOVEMBER 25, 2015

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 15.1.6.0 and later
Information in this document applies to any platform.

Goal

P6 EPPM R15.1 Patchset 6 implements an enhancement of a setting for "Hide Empty Projects Or WBS Threshold" to control the opened projects to be displayed or not displayed in the Activities view.  This article explains how it works.

 

 

Solution