Microsoft Project (MSP) XML Import Creates Duplicate Activities When Import Action Is Update Existing. (Doc ID 2077232.1)

Last updated on JANUARY 25, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 8.4.6.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 8.4.6.0 and later
Primavera P6 Professional Project Management - Version 8.4.6.0 and later
Information in this document applies to any platform.

Symptoms

On:  8.4.6.0 version, Cloud: P6 Client Application

ACTUAL BEHAVIOR
---------------
Export project to Microsoft Project (MSP) XML 2010, user opens in MSP 2010 and updates Activities. Saves the file as XML and when this XML is imported back into P6, all Activities are duplicated.

EXPECTED BEHAVIOR
-----------------------
For the import to not duplicate the Activities.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms