How to Create a Report Showing Summary Cumulative Cost in a Tabular Format for an Entire Project (Doc ID 2081307.1)

Last updated on JANUARY 30, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 7.0 to 15.2.2.0 [Release 7.0 to 15.2]
Information in this document applies to any platform.

Goal

How to create an S Curve Summary Report in a tabular format that displays total Cumulative Early and Late Cost on a monthly basis for the entire project.
 

Solution