Error: "<Date><Time> Is Not a Valid Date/Time Value" When Changing Any Date. (Doc ID 2081784.1)

Last updated on NOVEMBER 24, 2015

Applies to:

Primavera P6 Professional Project Management - Version 15.2.0.0 and later
Information in this document applies to any platform.

Symptoms

On : 15.2.0.0 version, P6 Client Application

When attempting to change any date, the following error occurs.

ERROR
-----------------------
 "<Date><Time> is not a valid date/time value"

STEPS TO REPRODUCE:
1. Go to Edit, User Preferences, Dates tab.
2. Uncheck the box for "Leading Zero" and "Show minutes". Check the box for "12 hour" under "Time".
3. Click Close to exit the User Preferences.
4. Go to Enterprise, Projects.
5. Go to the Dates tab in the Project Details at the bottom of the Layout.
6. Change the Data Date to any single digit hour. For example: 9 AM.
7. You will receive an error "...is not a valid date/time value".
8. Go back to the User Preference, Dates tab and check the box for "Leading Zero" or check the box for "Show Minutes".
9. Change the Data Date to any single digit hour. For example: 9 AM. That will be successful.
10. The same error occurs for scheduling if you try to change the time.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms