Symptoms

ACTUAL BEHAVIOR
---------------
P6 Baseline dates are not sent to the Unifier Schedule Sheet

EXPECTED BEHAVIOR
-----------------------
P6 Baseline data is brought over to Unifier from P6 successfully.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. A user adds values in appropriate P6 fields (e.g. BL Project Start, BL Project Finish, BL Duration)
2. Correctly maps identified baseline fields
3. Sends the data from P6 to Unifier, success message
4. Then reviews the Baseline Start, Baseline Finish and Baseline Duration fields in Unifier

BUSINESS IMPACT
-----------------------

Due to this issue, users cannot map P6 baseline data to Unifier.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms