My Oracle Support Banner

EBS - PS: Temporal Precedence Prior & Next Defined In EBS Discrete Job Is Not Reflecting In The PS Work Order (Doc ID 2091684.1)

Last updated on MARCH 30, 2017

Applies to:

Oracle Production Scheduling - Version 12.1.3.8 and later
Information in this document applies to any platform.

Goal

The precedence constraints on the operation diagram does not populates properly, why ?
In EBS work order Operation is defined with PRIOR operation but in PS temporal precedence is populated as Start at End or Start after End instead of Ends at End.
 

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.