EBS - PS: Temporal Precedence Prior & Next Defined In EBS Discrete Job Is Not Reflecting In The PS Work Order (Doc ID 2091684.1)

Last updated on MARCH 30, 2017

Applies to:

Oracle Production Scheduling - Version 12.1.3.8 and later
Information in this document applies to any platform.

Goal

The precedence constraints on the operation diagram does not populates properly, why ?
In EBS work order Operation is defined with PRIOR operation but in PS temporal precedence is populated as Start at End or Start after End instead of Ends at End.
 

Solution