Risk Register Impacts Change When Importing Into Plans With Different Planning Units

(Doc ID 2092394.1)

Last updated on JULY 31, 2017

Applies to:

Primavera Risk Analysis - Version 8.7.0070 and later
Information in this document applies to any platform.


When importing a Risk Register created with daily planning units into a plan with hourly planning units, the impacts in the Risk Register become much smaller. Similar behavior is seen if the opposite is done where the Risk Register created in a plan with hourly planning units is imported into a daily planning unit plan. The impacts become larger.

Expect Risk Register impacts to stay consistent regardless of planning unit of the imported schedule.

The issue can be reproduced at will with the following steps:
1. Create a Risk Register in plan with daily planning units.
2. Import Risk Register into a plan with hourly planning units.
3. Impacts will be much smaller.


Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms