Complete Button not Enabled When Both Instructed and Non-Instructed Steps are Selected in Switching (Doc ID 2097021.1)

Last updated on JUNE 13, 2016

Applies to:

Oracle Utilities Network Management System - Version 1.12.0.2 to 1.12.0.3 [Release 1.12]
Oracle Network Management for Utilities - DMS - Version 1.12.0.2 to 1.12.0.3 [Release 1.12]
Information in this document applies to any platform.

Symptoms

When attempting to complete the steps of a switch plan, the Complete button does not get enabled when a combination of Instructed and Non-Instructed steps are selected.

The issue can be reproduced using following steps:

1. Create a switch plan with several steps.
2. Transition the sheet to "Issued" status.
3. Select the first step and instruct it.
4. Select the first and second steps.

At this point, the Complete button is disabled/desensitized.

Cause

Sign In with your My Oracle Support account